The Senate has raised alarm over the sharp increase in the cost of the Talanta Sports City project, which has risen from Sh35 billion to Sh45.85 billion.
The Senate Standing Committee on Roads, Transportation and Housing has now written to Sports Cabinet Secretary Salim Mvurya, seeking a full explanation on the project’s status and how it is being managed.
The committee’s concerns follow issues flagged by the Auditor-General in a report for the financial year ending June 2025.
According to the senators, the additional Sh10.85 billion has not been properly explained and lacks enough supporting documents.
The audit report also revealed that the contract for the project was awarded through direct procurement, instead of following the required competitive tendering process under Kenyan law.
Further concerns were raised over the lack of approval from the Attorney-General for contracts exceeding Sh5 billion, raising questions about whether proper legal procedures were followed.
The committee, led by Chairman Senator Eddy Oketch, is now demanding transparency and accountability in the handling of the multi-billion project.
“We request your office to provide a comprehensive response addressing the procurement process, cost variations, financing structure, and implementation status of the Talanta Stadium project,” said Oketch.
The Talanta Sports City project is a key facility as Kenya prepares to host major international tournaments, but the rising costs and procurement concerns are now putting
You may also like
FOOTBALL
FOOTBALL
FOOTBALL
VOLLEYBALL
World Athletics has unveiled demanding qualification standards for the 2028 Los Angeles Olympic Games, giving...
Kenyan fencing youngster Aliyah Makena is determined to build on her experience at the Dakar...